COVID-19 PRODUCTIVITY REPORT March June 2020 Citizens Advisory - - PowerPoint PPT Presentation

covid 19 productivity report
SMART_READER_LITE
LIVE PREVIEW

COVID-19 PRODUCTIVITY REPORT March June 2020 Citizens Advisory - - PowerPoint PPT Presentation

COVID-19 PRODUCTIVITY REPORT March June 2020 Citizens Advisory Committee August 19, 2020 Agenda Item #8 WFH NOT US? Over 50 projects completed Track Installed new walkway rock at 12 station tracks SF (10) Stations New bird


slide-1
SLIDE 1

COVID-19 PRODUCTIVITY REPORT March – June 2020 Citizens Advisory Committee August 19, 2020 Agenda Item #8

slide-2
SLIDE 2

WFH NOT US? Over 50 projects completed…

  • Track – Installed new walkway rock at 12 station tracks SF (10)
  • Stations – New bird netting at Airport Avenue & Taylor Street

(13)

  • Right of Way – New fencing in SF at Iowa St, Pennsylvania &

Palou Ave, San Carlos man & vehicle gate (5)

  • Communications – Dragger equipment software upgrade (13)
  • Signal – Installed solid state Circuit Controller at 3rd Ave (13)
slide-3
SLIDE 3

TRACK SOGR

  • Worked with Operations to utilize NEW Work Windows,

as Passenger Service was reduced, our focus was on the following:

  • 1. Track Maintenance
  • 2. Track Upgrades
  • 3. Capital Project Support
slide-4
SLIDE 4

22nd St. Rail Replacement

  • Rail fracture at MP 1.60 on the

MT2 track, West Rail

  • Fracture occurred on

12/4/2019 under Train number 102 Southbound

  • Track back into service 3

hours later

  • Rail produced in early 1970’s,

standard AREA 136 LB Rail

slide-5
SLIDE 5

22nd St. Fractured Rail Lab Photos

slide-6
SLIDE 6

22nd St. Rail Replacement

  • Approximately 5000 Lineal

Feet of rail removed and

  • replaced. With no impact to

train operations.

slide-7
SLIDE 7

Thermite Welding in Track

slide-8
SLIDE 8

Thermite Welding in Track

slide-9
SLIDE 9

The Completed Weld

slide-10
SLIDE 10

New Rail Lubricator at MP 9.51 MT2

slide-11
SLIDE 11

CP Shark Switch 7A Spring Frog Replacement

slide-12
SLIDE 12

South San Francisco Crossover Removals

slide-13
SLIDE 13

25th Ave. Track Stabilizing Support

slide-14
SLIDE 14

CP Shark Tie Replacement

  • CP Shark Switch 5 and 5A

removed from service

  • Long ties(10’ -16’) removed

and replaced with 9’ ties to allow for PCEP construction work

slide-15
SLIDE 15

San Mateo Bridges – Walkway Installation

  • California Public Utilities

Commission(CPUC) issued correction notice

  • CPUC walkways were not

constructed during the San Mateo Bridges project in 2017

  • Minimum of 8:1 sloped ramps

required for walkways

  • 4 walkways required at each

bridge, 16 total

slide-16
SLIDE 16

Crash Beam Strike At Tilton Ave.

  • This is what a bad Friday

really looks like…

  • Expect the unexpected when

working around the railroad

slide-17
SLIDE 17

Questions?