SLIDE 1
SustainTech – Saskatoon, SK March 21, 2019 Kevin French
Case Study: How to Avoid Failures in the Design and Installation of Permeable Reactive Barriers
SLIDE 2 Presenter
Kevin French, P.Eng
- Vice President, Vertex Environmental Inc.
- B.A.Sc., Civil/Environmental Engineering, University of Waterloo
- 30+ years environmental engineering; 25 in consulting and 5 as a
remedial contractor Special thanks to Milestone Environmental Contracting Inc. who were our partners for this project.
Vertex Environmental Inc.
- Founded in 2003
- Specialized Environmental Remediation
Contracting
- High Resolution Site Characterization (HRSC)
SLIDE 3
Vertex Environmental Inc.
SLIDE 4 Presentation Overview
- Permeable Reactive Barriers
- Overview of Site Conditions
- Preliminary Design & Bench-Scale Testing
- High-Resolution Site Characterization
- Updated Final Design
- Full-Scale Installation
- Quality Assurance / Quality Control
- Performance Monitoring
- Lessons Learned
- Questions
SLIDE 5
Permeable Reactive Barriers (PRBs)
SLIDE 6 Permeable Reactive Barriers (PRBs)
contaminated groundwater plumes (passive)
- Allow groundwater to flow through
unimpeded
- Different reactive media for
different contaminants
- Original zero-valent iron (ZVI)
PRBs (“Iron Walls”) installed in mid-1990 still functional
- Can be dug or injected
- Sustainable (no energy use to
- perate)
SLIDE 7
Overview of Site Conditions
SLIDE 8
Overview of Site Conditions
SLIDE 9 Overview of Site Conditions
- Contamination identified in 1998
- Municipality purchased in 2008 and converted to parking lot
- Main groundwater contaminants were tetrachloroethylene
(PCE) and its degradation products
- No DNAPL suspected
- Main pathway of concern was groundwater flow through
- verburden
- Remedial objective was to prevent plume of contaminated
groundwater from continuing to migrate
SLIDE 10
Overview of Site Conditions
PCE concentrations in groundwater April 2012
1000 100 500
SLIDE 11 Overview of Site Conditions
– Sand and gravel fill with occasional cobbles – Native soil was sand, silty sand and silty clay till – Some reported “flowing” sands – Clay till served as “confining layer” over limestone / dolostone bedrock – Overburden thickness was approximately 6 to 7 mbgs
– Water levels in the overburden at approx. 2.4 to 3.4 mbgs – Horizontal hydraulic gradient of approx. 0.03 to 0.06 – Hydraulic conductivity of approx. 1.2E-07 to 3.5E-04 m/s – Estimated groundwater flow velocity of 40 m/yr
SLIDE 12
Overview of Site Conditions
Geologic Cross-Section
SLIDE 13
Preliminary Design & Bench-Scale Testing
SLIDE 14
Preliminary Design
SLIDE 15
Preliminary Design
Gate Funnel Funnel
SLIDE 16
Preliminary Design
SLIDE 17 Bench-Scale Testing
- The municipal client did not have
experience with ZVI PRB technology
- Bench-scale treatability testing was
- ffered to provide “proof-of-concept”
and assurances to client
groundwater obtained from the site and mixed with ZVI and sand
SLIDE 18 Bench-Scale Testing
degradation half-lives calculated based on bench-scale tests
references as a reality check
total CVOCs achieved
SLIDE 19 Preliminary Design & Bench-Scale Testing
- Preliminary PRB design was determined using a computer model that
assessed: – CVOC concentrations in groundwater and target treatment concentrations – Physical, geological and hydrogeological conditions of the soils at the site and in the planned PRB – CVOC half-lives from the bench-scale testing (first order decay) – Groundwater temperature conditions for site – Groundwater flux balance through “funnel & gate” PRB configuration
- In order to meet PSS levels using reported groundwater flow velocities a
PRB 1.0 m thick would need to contain 37% ZVI
SLIDE 20 Preliminary Design & Bench-Scale Testing
- Sensitivity analysis completed on
all input variables
- Model (and therefore results)
most sensitive to hydraulic conductivity
- k-values varied by over 3 orders
- f magnitude, other parameters
by <1
- Recommended additional site
characterization to reduce uncertainty in predicted results
Value used in model
SLIDE 21
High-Resolution Site Characterization
SLIDE 22 High-Resolution Site Characterization
Hydraulic Profiling Tool (HPT)
- Direct-push
- Assess formation permeability
- Water injected into the ground; flow and
back-pressure measured
- EC: Estimate of soil type
- Identifies location of water table (no wells)
- Result: Empirical estimate of hydraulic
conductivity on a cm scale
- HPT deployed at the site to find preferential
flow paths in the saturated zone and to define lower “confining layer”
SLIDE 23
High-Resolution Site Characterization
SLIDE 24
High-Resolution Site Characterization
SLIDE 25
High-Resolution Site Characterization
How to keep water from freezing in a 0.25” diameter line when the temperatures on-site are -10 to -20°C?
SLIDE 26
High-Resolution Site Characterization
SLIDE 27
High-Resolution Site Characterization
Unsaturated Zone Higher K Zone Lower K Zone Confining Layer
SLIDE 28
Updated Final Design
SLIDE 29 Updated Final Design
- Data from the HPT testing activities was used to update the preliminary
design for the PRB:
- In order to meet PSS reduction using updated site data a PRB containing
30% ZVI would now only need to be 0.9 m thick (~27% savings)
SLIDE 30
Full-Scale Installation
SLIDE 31 Full-Scale Installation
- Cut and fill method PRB
- Concrete wing walls for “Funnels”
were 12 m long and 6 m long
- Cut / fill (using trench box) the
“Funnel” wing walls with concrete
- Excavate PRB “Gate” section using
biopolymer slurry (guar gum) for sidewall support
- Coarse sand for PRB “Gate”
delivered in cement mixing truck; ZVI added to truck and blended
SLIDE 32 Full-Scale Installation
- Backfill PRB “Gate” section with
ZVI / sand mixture and avoid gravity separation through slurry
- Break slurry and pump back from
trench into on-site tank for off-site disposal
- Place and compact granular trench
cap and repave
- Completed over 6 days on-site
SLIDE 33
Full-Scale Installation
SLIDE 34
Full-Scale Installation
SLIDE 35
Full-Scale Installation
SLIDE 36
Full-Scale Installation
SLIDE 37
Quality Assurance / Quality Control
SLIDE 38 Quality Assurance / Quality Control
- Samples of ZVI / sand mixture
collected from each batch and subjected to magnetic separation testing
- Post-installation boreholes drilled
through “Gate” portion of PRB and subjected to magnetic separation testing (similar results)
- One monitoring well drilled approx.
1.5 m downgradient of PRB for groundwater sampling and analysis Target ZVI Concentration = 30%
SLIDE 39
Performance Monitoring
SLIDE 40
Performance Monitoring
Groundwater Flow Direction
SLIDE 41 Performance Monitoring
PSS for PCE PSS for TCE
SLIDE 42 Performance Monitoring
PSS for PCE PSS for TCE
SLIDE 43 Performance Monitoring
Generic Standards Met!
PSS for PCE PSS for TCE SCS for VC SCS for PCE, TCE & DCE
SLIDE 44
Lessons Learned
SLIDE 45 Lessons Learned
- Review ESA data, develop CSM and preliminary
design (data gaps, sensitivity, etc.)
- Bench-scale testing for site-specific response
- Collect additional site data (HPT) to resolve
uncertainties (confining layer, k values)
- Ensure no gravity separation of ZVI / sand admixture
as it is emplaced
- Implement robust QA/QC programme during and post-
installation
- Ensure field installation is as per final design
SLIDE 46
Questions?
Thank You for Your Time
Kevin French
Vertex Environmental Inc. (519) 653-8444 x 303 (519) 404-5442 mobile kevinf@vertexenvironmental.ca www.vertexenvironmental.ca