Bruny Island Energy Forum March 2020 Agenda The CONSORT project: - - PowerPoint PPT Presentation

bruny island energy forum
SMART_READER_LITE
LIVE PREVIEW

Bruny Island Energy Forum March 2020 Agenda The CONSORT project: - - PowerPoint PPT Presentation

Bruny Island Energy Forum March 2020 Agenda The CONSORT project: learnings and outcomes The cable: Current status, future plans Round table discussion Trial on a page ARENA funded Under Research & Development round ~7.9m total


slide-1
SLIDE 1

March 2020

Bruny Island Energy Forum

slide-2
SLIDE 2

Agenda

  • The CONSORT project: learnings and outcomes
  • The cable: Current status, future plans
  • Round table discussion
slide-3
SLIDE 3

Trial on a page

ARENA funded

Under Research & Development round ~7.9m total value. $2.9m ARENA funding April 2016 – April 2019

3 year research/2 year trial Manage cable load and Diesel use Collaboration: ANU, USyd, UTAS, Reposit Power, TasNetworks ~150 kW battery capacity ~35 customers

slide-4
SLIDE 4

The network

slide-5
SLIDE 5

Installation

slide-6
SLIDE 6

Technically: how did we go?

slide-7
SLIDE 7

Controlling a battery for fun and profit

Electricity price (tariff) Solar generation Battery actions (charge/discharge)

Icons made by Freepik, prettycons from www.flaticon.com is licenced by CC 3.0 BY

The Reposit controller takes inputs And determines how to use them to save money using the battery

slide-8
SLIDE 8

Controlling a battery for fun and profit – network version

Electricity price (tariff) Solar generation Battery actions (charge/discharge) Now battery also responds to network events

Icons made by Freepik, prettycons from www.flaticon.com is licenced by CC 3.0 BY

Add a network input Network constraint

slide-9
SLIDE 9

Value-reflective payments

slide-10
SLIDE 10

What’s phase anyway?

Customers are connected between two phases But only one phase is constrained

slide-11
SLIDE 11

Why participate? Drivers

Financial Environment/Sustainability Community care/value Interest in technology Desire to be part of the trial

slide-12
SLIDE 12

And how did you feel about it all?

Relaxed, confident with minimal criticisim 3% Relaxed, confident with some criticisim 70% Anxious, cautious but

  • ffset by other

benefits 21% Anxious, cautious and unconvinced 6%

slide-13
SLIDE 13

What’s next – for demand response

  • Operationalisation

 Reduce cost  Increase diversity of sources

  • Explore other parts of the network
  • East coast
slide-14
SLIDE 14

What’s next – for Bruny Island

  • Participants  Customers own Solar/battery systems. While

cable is being replaced demand response is still valuable

  • Cable failure/future plans  Michael will talk about
slide-15
SLIDE 15

What happened, what’s next Presenter: Michael Verrier – Senior Asset Strategy Engineer

Cable Failure

slide-16
SLIDE 16

Tinderbox-Dennes Point 11kV submarine cable fault

slide-17
SLIDE 17

Tinderbox-Dennes Point 11kV submarine cable fault

  • On Saturday 2nd November, a red phase to earth fault occurred
  • Testing confirmed that the fault was within the submarine cable.
  • Divers were sent down to investigate at estimated location.
  • What they found…….
slide-18
SLIDE 18

Tinderbox-Dennes Point 11kV submarine cable fault

Video of suspect @ 13:26

Faulted section Original cable sample

slide-19
SLIDE 19

Tinderbox-Dennes Point 11kV submarine cable fault

  • We have mobilised additional diesel generators to support the

island under contingency situations.

  • We have recently installed more remote operated devices on

Bruny Island which will assist with faster restoration times should a fault occur.

slide-20
SLIDE 20

Tinderbox-Dennes Point 11kV submarine cable fault

  • There is a need to replace the failed cable now to return to a

secure supply arrangement.

  • We have sent divers down to inspect and report back on the

remaining in-service cable.

slide-21
SLIDE 21

Tinderbox-Dennes Point 11kV submarine cable fault - replacement

  • Lots to consider, including;
  • Marine survey (Bathymetry)
  • Geotech survey
  • Heritage, aboriginal and environmental considerations
  • On-land considerations
  • Feeder and substation demands
  • Route/s
  • Constructability - Specialised installation method and crew
  • Operability
  • Maintainability
slide-22
SLIDE 22

Tinderbox-Dennes Point 11kV submarine cable fault - replacement

slide-23
SLIDE 23

Future plans

Presenter: Michael Verrier

slide-24
SLIDE 24

Future plans

  • We are still undertaking preliminary investigations into

maintaining security of supply to Bruny Island

  • This includes investigating replacing the second cable and

alternatives.

  • We are committed to engaging with all stakeholders once there

is more information to share.

  • And expect we will be in a position to share more information on

the failed cable replacement with you again early in the new financial year

slide-25
SLIDE 25

Future plans

  • You can contact our customer contact centre at any time on

1300 137008 to discuss further with us.

slide-26
SLIDE 26

Discussion starters: questions

  • About CONSORT
  • Did any learnings surprise you? Is there perspective you can add?
  • About demand response
  • As our only active demand response scheme: Can you give us any

thoughts on a wider rollout?

  • About the cable failure:
  • Any burning questions on future Island supply needs?
slide-27
SLIDE 27

Thank you