BRIEFING BRIEFING ON ON WATTS WATTS BAR BAR UNIT UNIT 2 2 - - PowerPoint PPT Presentation

briefing briefing on on watts watts bar bar unit unit 2 2
SMART_READER_LITE
LIVE PREVIEW

BRIEFING BRIEFING ON ON WATTS WATTS BAR BAR UNIT UNIT 2 2 - - PowerPoint PPT Presentation

BRIEFING BRIEFING ON ON WATTS WATTS BAR BAR UNIT UNIT 2 2 LICENSE LICENSE APPL APPLICATION ICATION REVIEW REVIEW October 30, 2014 Mark Satorius Executive Director for Operations U.S. Nuclear Regulatory Commission Watts Bar 2


slide-1
SLIDE 1

BRIEFING BRIEFING ON ON WATTS WATTS BAR BAR UNIT UNIT 2 2 LICENSE LICENSE APPL APPLICATION ICATION REVIEW REVIEW

October 30, 2014 Mark Satorius Executive Director for Operations U.S. Nuclear Regulatory Commission

slide-2
SLIDE 2

Watts Bar 2 Overview

William Dean, Director Office of Nuclear Reactor Regulation

2

slide-3
SLIDE 3

AGENDA

  • The Part 50 Process and Watts

Bar’s Unique History

  • Licensing Framework and Status
  • f Licensing Review
  • Construction Program Overview
  • Status of Inspection Activities

3

slide-4
SLIDE 4

WRAG Provides Oversight and Management Direction to Ensure Unit 2 Meets All Relevant Requirements

4

WRAG Public Outreach Meeting September 2014 WRAG Observes Construction Progress of FLEX Building

slide-5
SLIDE 5

Watts Bar 2 Part 50 Process and Watts Bar Licensing History

Michele Evans, Director

Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

5

slide-6
SLIDE 6

The Part 50 Process – An Overview

  • Construction Permits and

Operating License Issued Separately

  • Path Forward for Commission

Granting Authority to NRR

6

slide-7
SLIDE 7

Watts Bar’s Unique History Has Defined the Project

  • Construction Permit Issued for Units 1

and 2 in 1973

  • Operating License Application

Submitted for Units 1 and 2

  • Hearing for Construction Permit;

Operating License Opportunity for Hearing

  • Work Stoppage in 1985
  • Full Power Operating License for Unit 1

in 1996

  • Resume Construction on Unit 2 in 2007

7

slide-8
SLIDE 8

Watts Bar 2 Licensing Framework and Status of Licensing Review

Justin Poole Senior Project Manager

Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

8

slide-9
SLIDE 9

Established Clear Framework for Licensing

  • SRM-SECY-07-0096 Provided

Commission Direction on aligning the licensing basis

  • Issued NRR Office Instruction

LIC-110 to guide staff review

  • Regulatory Framework Review

and Issuance of Safety Evaluation Report Supplement 21

9

slide-10
SLIDE 10

Majority of the Licensing Review Has Been Completed

10

slide-11
SLIDE 11

Remaining Licensing Actions to Support a Licensing Decision

  • Completion of Hydrology Review
  • Review of As-Built Fire Protection

Report

  • Closure of Open Items of Interest

to the Advisory Committee on Reactor Safeguards

  • Implementation of Continued

Storage Rulemaking

  • Review of Fukushima Orders

11

slide-12
SLIDE 12

Major Milestones for the NRC Staff to Accomplish Prior to Licensing

Operating License Decision

Commission Notation Vote Paper

(30 – 60 days prior to OL decision)

Advisory Committee

  • n Reactor

Safeguards Recommendation

Final Regional Readiness Letter

(30 days prior to OL decision)

12

slide-13
SLIDE 13

Watts Bar 2 Construction Inspection

Victor McCree Regional Administrator NRC Region II

13

slide-14
SLIDE 14

Dev Developed eloped a Cu a Custo stomized mized Cons Construction truction Inspection Inspection Program Program

  • Credited previously completed

inspections

  • Addressed legacy programmatic

issues and refurbishment

  • Comprehensively addresses

remaining activities, including new requirements

14

slide-15
SLIDE 15

15

5,000 10,000 15,000 20,000 25,000 2008 2009 2010 2011 2012 2013 2014

Subst Substan antial In tial Inspe spect ction ion Ef Effor

  • rt E

t Exp xpen ende ded on d on Watts tts Bar Bar Unit Unit 2

Projected Hours Actual Hours

15

slide-16
SLIDE 16

Watts Bar 2 Construction Inspection

Tomy Nazario Senior Resident Inspector Watts Bar 2

16

slide-17
SLIDE 17

Inspections Inspections On On-Track to Track to Supp Support Lic

  • rt Licensing

ensing Decision Decision

  • Majority of construction

inspections completed

  • Good progress on inspections of

historical and unique Unit 2 items

  • Inspections of operational

readiness and new requirements (cyber, Fukushima) planned

17

slide-18
SLIDE 18

Verifying Verifying Construct Construction ion to to Licensi Licensing Basis ng Basis

  • Reactor Vessel Reassembly
  • As-Built Verifications

18

Inspection of Reactor Vessel assembly Inspection of full flow filter

slide-19
SLIDE 19

Verifying Verifying Refurbishment Refurbishment Activities Activities

  • Key to addressing aging questions
  • Equipment replacement and repair

19

Inspector entering the reactor coolant pump bowl Receipt/Storage inspection of vital inverter

slide-20
SLIDE 20

Verifying Verifying Implementation of Implementation of Recent Recent Requirement Requirements

  • Inspection of Cyber Security

Requirements

  • Inspection of Mitigating Strategies

Order

20

Inspection of rebar placement Inspection of vent installation

slide-21
SLIDE 21

Overall Overall Construct Construction ion Activities Activities Have Met Have Met Requirement Requirements s

  • Plant built according to design
  • Inspections have added value
  • Currently no potentially significant
  • pen issues or findings

21

slide-22
SLIDE 22

Closing Remarks

22

Bill Dean and Vic McCree Tour of Unit 2 Control Room Bill Dean and Vic McCree Tour of Unit 2 Ice Condenser

slide-23
SLIDE 23

Acronyms Acronyms

  • NRC – Nuclear Regulatory

Commission

  • NRR – Office of Nuclear Reactor

Regulation

  • OL – Operating License
  • SECY – Office of the Secretary
  • SRM – Staff Requirements

Memorandum

  • WRAG – Watts Bar Reactivation

Group

23

slide-24
SLIDE 24

Backup Slides Backup Slides

24

slide-25
SLIDE 25

Major Major Milestone Milestone Timeli Timeline ne

25

slide-26
SLIDE 26

Reactor Oversight Reactor Oversight Process Process Transi Transition tion Pla Plan

  • Transition will be on an individual

cornerstone basis

  • Four of seven cornerstones

expected to be transitioned at license issuance

  • Performance indicator validity

addressed with additional inspections

26