board of visitors audit compliance and risk committee
play

Board of Visitors Audit, Compliance, and Risk Committee September - PowerPoint PPT Presentation

Board of Visitors Audit, Compliance, and Risk Committee September 2018 1 Construction Management: Financial Controls and Project Monitoring 1. Overview of Business 2. Construction Process 3. University Hospital Expansion Project 4.


  1. Board of Visitors Audit, Compliance, and Risk Committee September 2018 1

  2. Construction Management: Financial Controls and Project Monitoring

  3. 1. Overview of Business 2. Construction Process 3. University Hospital Expansion Project 4. Audit Report

  4. Overview of Business

  5. FACILITIES GROWTH 5

  6. CONSTRUCTION SPENDING 6

  7. ACTIVE CONSTRUCTION VOLUME Number o of A Acti tive P Projects ts Q1 Q1 Q2 Q2 Q3 Q3 Q4 Q4 FY1 Y18 C Capital 59 64 70 73 FY18 No Non-Cap apital al 148 155 175 205 FY18 Volume A Act ctive P Project cts 278 FY17 Volume A Act ctive P Project cts 167 FY16 Volume A Act ctive P Project cts 94 Value o of A Acti tive P Projects ts Q1 Q1 Q2 Q2 Q3 Q3 Q4 Q4 FY1 Y18 C Capital $ 1,407,524,551 $ 1,448,421,051 $ 1,460,019,051 $ 1,469,629,051 FY18 No Non-Cap apital al $ 65,072,931 $ 67,001,568 $ 71,702,359 $ 75,834,742 FY1 Y18 Value o of A Acti tive P Projects $ 1,545,463,793 FY1 Y17 Value o of A Acti tive P Projects $ 1,406,903,052 FY1 Y16 Value o of A Acti tive P Projects $ 967,994,956 7

  8. Construction Process

  9. CONTRACTING OPTIONS Competitive Negotiation (RFP) Process • Competitive Negotiation Contractor – Fixed Price • Construction Management – At Risk with Design Phase Services • Construction Management – Agency with Design Phase Services • Design (Completion)/Build Special Circumstances • Sole Source • Emergency Competitive Sealed Bid • Health System & Academic On-Demand Invitation for Bids 9 • Select Bidders for Competitive Sealed Bid • Prequalification for Competitive Sealed Bid

  10. CONTRACTING CM Design Phase Subcontractor Fixed Price Procurement Services Procurement Contract 10

  11. CM SELECTION: UHE PROJECT Receive Project 9 Responses 4 Firms Issue RFP and Spring 2014 Proposals and Select CM Received Shortlisted Site Visit Advertisement Interview Selection Criteria: Technical 90% • Key Personnel Experience and Qualifications 30% • Past Performance and Experience 20% • Management Capability/Project Plan 20% • BIM Experience 10% • Project Safety Record & Proposed Plan 10% • SWaM Firm Utilization 10% Selection Criteria: Price 10% 11

  12. DESIGN ASSIST SELECTION: UHE PROJECT Selection Criteria: • DA selection process is similar to CM selection. Safety • Key personal • Major Design Assist Packages include Electrical, Past performance Structural Steel, Mechanical, Plumbing and Deep • Management Capabilities Foundations • BIM • SWaM Design Assist packages were awarded on August • Quality Control 21, 2015, based on the Schematic Documents • LEED prepared by Perkins + Will dated 2/27/15 • Pricing 12

  13. University Hospital Expansion Project

  14. 14

  15. 2013 2014 2015 2016 2017 2018 2019 2020 2021 • Project Approval • SD Approval Construction Construction Plinth Tower Renovations • Procure A/E • Procure DA Procure CM Start – site Start – Building • Program • Enabling Complete Complete Complete package package Development construction 15

  16. 16

  17. 17

  18. WEBCAM AUGUST 2018 HTTPS://YOUTU.BE/_SHYRZDLWXC 18

  19. Audit Report

  20. AUDIT REPORT Ratings for Internal Audit Testing Results A Priority 1 item signifies a control and/or process deficiency of sufficiently high risk that it provides minimal or no assurance that 1 Priority 1 0 institutional objectives will be achieved. Management must take immediate corrective action to mitigate Priority 1 deficiencies. A Priority 2 item signifies a control and/ or process deficiency that hinders the effectiveness and efficiency of operations, 4 2 Priority 2 potentially impeding the attainment of institutional objectives. Observations Management must take timely corrective action to mitigate Priority 2 deficiencies. Process A process improvement item signifies an opportunity to achieve 12 PI Improvement additional control and/or process efficiencies. Recommendations 20

  21. AUDIT REPORT Priority 2 observations: • CM mark-ups on multiple contracts • Payment and Performance Bonds for Bell Company subcontract • Change order processing • Design-assist subcontracting 21

  22. Enterprise Risk Management Program Report 2019 Goals

  23. ERM – September 2018 Update F Y 19 G o a l s • Goal #1 - Further on-boarding The College at Wise • Goal #2 - Building key-risk interaction tools and map • Goal #3 - Moving ERM data and processes into a governance, risk, and compliance (GRC) system being implemented by Audit • Goal #4 - Revising the annual ERM cycle and governance structure 24

  24. ERM Goal #1 - Further Onboarding UVA-Wise T i m e l i n e a n d Ne t w o r k o f S t a k e h o l d e r s 2018 2018 2018 2019 2019 Aug/Sept Oct/Nov Nov/Dec Jan/Feb Mar/ongoing Risk Risk Clarify Risk Risk Response/ Identification Management Strategic Assessment Ownership Objectives and Monitoring BOV Wise Committee College Advisory Board Risk Management Council (Chancellor’s Senior Staff) Risk Management Network (Unit Leaders) 25

  25. ERM Goal #2 – Building key-risk interaction tools Key Risk Environment OWNERSHIP IMPACTING IMPACTED SUPPORTING UNITS 26

  26. ERM Goal #3 – Implementing ERM System Goal #3 l #3 - Moving ERM data and processes into the governance, risk, and compliance (GRC) system being implemented by Audit 27

  27. ERM Goal #4 – Streamlining the Annual ERM Cycle and Governance Goal #4 l #4 - Revis ising ing t the annual e annual E ERM c cycle e and and gover ernan nance e structure • Updating Risk Management Networks (RMN) purposes and membership • Streamlining emerging risk identification and reducing administrative burden 28

  28. Written Reports

  29. CLOSED SESSION REPORTS

  30. RETURN TO PUBLIC SESSION

  31. Committee Meeting Adjourns

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend