bepcii besiii and physics goals
play

BEPCII/BESIII and Physics Goals Flavour in the Era of the LHC May - PowerPoint PPT Presentation

BEPCII/BESIII and Physics Goals Flavour in the Era of the LHC May 15-17, 2006 David Asner Asner David Carleton University Carleton University For the BES For the BES Collaboration Collaboration 1 The Beijing Electron Positron Collider


  1. BEPCII/BESIII and Physics Goals Flavour in the Era of the LHC May 15-17, 2006 David Asner Asner David Carleton University Carleton University For the BES For the BES Collaboration Collaboration 1

  2. The Beijing Electron Positron Collider (BEPC) L ~ 5 × 10 30 /cm 2 ⋅ s at J/ ψ E cm ~ 2 - 5 GeV A unique e + e - machine in the τ -charm energy region after CLEO-c.

  3. BEPCII: a high luminosity double–ring collider SC RF Two rings tunnel 3 Government approved, and started construction at end of 2003

  4. BEPCII Design goal Energy range 1 – 2.1 GeV Optimum energy 1.89 GeV 1 x 10 33 cm -2 s -1 @ 1.89 GeV Luminosity Full energy injection: 1.55 � 1.89 GeV Injection Positron injection speed > 50 mA/min Synchrotron mode 250 mA @ 2.5 GeV Dual purpose machine 4

  5. Design Goals and Main Parameters 5

  6. e + -e - Colliders: Past, Present and Future 10 37 L (cm -2 s -1 ) -2 sec -1 ) SUPER L (cm FACTORIES 10 36 KEK B and PEP II 10 35 GLC 10 34 KEK B PEP II DAFNE2 FACTORIES BEPCII 10 33 CESR CESRc LEP DAFNE 10 32 TRISTAN VEPP2000 PETRA DORIS 10 31 VEPP4M BEPC SPEAR COLLIDERS VEPP2M 10 30 ADONE E cm (GeV) 10 29 E (GeV) 1 10 100 1000 6

  7. BEPCII Major Milestones • In 2004, Completed – Upgrade of Linac ; – Moved BES from beam line, and dismounted ; – Improve infrastructure, including the power station 。 • Resumed synchrotron run ,t ill June, 05. • July. 05 – Sep. 06 : - Removed everything from ring ,t unnel improvement , water pipe and power outlets 。 finished 。 - Install the main ring components ,f rom 2 nd of March, 06 . • Sep. 06 – June. 07, ring commissioning, SCQ moved in later , Some synchrotron run. • Aug. 07, BESIII moved to the beam line. • Sep. 07 Commissioning ring and detector together. • Dec. 07 test run 。 • Dec. 08, to achieve a lum. of 3 × 10 32 cm -2 s -1 .

  8. BEPCII Status • BEPCII linac installation complete(new electron gun; new position source; new rf power (klystrons and modulators); and others. Most design specifications reached at 1 st test run. 8

  9. BEPCII Linac achieved Performances parameters Design (BEPC) Achieved Beam energy (G eV ) 1.89(1.55) 1.89 (e-); 1.55 (e+) 1) e+ 40(4) > 63 current (mA) e- 500(50) > 500 Repetition rate (Hz) 50(25) 25 ~ 50 e+ 1.60(1.70) 0.93 @ 1.89 GeV 2) Emittance (mm ⋅ e- 0.20(0.58) 0.30 @ 1.89 GeV 2) mrad ) e+ ± 0.5(0.8) ± 0.50 @ 1.89 GeV 2) Energy spread ( % ) ± 0.5(0.8) ± 0.55 @ 1.89 GeV 2) e- note :1)T wo rf power stations were not in operation at the time. 2 ) The values for 1.89 GeV is extrapolated from those of 1.30 GeV , should be measured when the energy is at 1.89 GeV.

  10. Status of Storage ring • Major magnets; super-conducting RF cavities and super-conducting quadrupole magnets, beam pipes; kicker; beam instruments; control system; vacuum system as well as the cryogenics; most of the systems have been completed; • Their installation is under way; ~ 14 magnet sets • Testing ring in Sep. 2006, without SCQ first; • Beam collisions expected in spring 2007. 10

  11. Magnet System Bending magnets Quadrupole magnets Sextupole magnets Dipole correctors 11

  12. Started the installation of magnet sets

  13. KEKB type SC Cavity

  14. Cavities delivered and being tested

  15. Super-conducting Quadra-pole

  16. BESIII Detector SC magnet Muon Counter TOF Be beam pipe Drift Chamber CsI(Tl) calorimeter 16

  17. BESIII Detector Two rings, 93 bunches: • Luminosity 10 33 cm − 2 s − 1 @1.89GeV 6 × 10 32 cm − 2 s − 1 @1.55GeV Magnet: 1 T Super conducting 6 × 10 32 cm − 2 s − 1 @ 2.1GeV MDC: small cell & He gas σ xy =130 µ m σ p /p = 0.5% @1GeV dE/dx=6% TOF: σ T = 100 ps Barrel 110 ps Endcap Muon ID: 9 layer RPC Data Acquisition: EMCAL: CsI crystal Δ E/E = 2.5% @1 GeV Event rate = 3 kHz Trigger: Tracks & Showers σ z = 0.6 cm/ √ E Pipelined; Latency = 6.4 µ s Thruput ~ 50 MB/s The detector is hermetic for neutral and charged particle with excellent resolution , PID adequate, and large coverage. 17

  18. MDC Parameters R inner: 63mm ; R outer: 810mm Length (out.): 2582 mm Inner cylinder: 1.2 mm Carbon fiber Outer cylinder: 11.5 mm CF with 8 windows Sense wire : 25 micron gold-plated tungsten (plus 3%Rhenium ) -- - 6796 Layers (Sense wire ): 43 Field wire: 110 micron gold-plated Aluminum --- 21884 Gas: He + C3H8 (60/40) ~ 130 m � µ x Cell: inner chamber --- 6 mm � outer chamber --- 8.1 mm P ~ 0 . 5 % @1GeV/C P � dE dx ~ 6 % dE Expected performance 18 dx

  19. MDC 19

  20. Wire Stringing Completed 20

  21. Beam test at KEK Prototype tested in a 1T magnetic field at KEK 12GeV PS last year. Results: • spatial resolution better than 130 µ m • cell efficiency over 98% • dE/dX resolution better than 5% (3 σ π /K separation exceeding 700MeV/c). 21

  22. CsI(Tl) crystal calorimeter • Design goals: – Energy: 2.5% @ 1GeV – Spatial: 0.6cm @ 1GeV • Crystals: – Barrel: 5280 w: 21564 kg – Endcaps: 960 w: 4051 kg – Total: 6240 w: 25.6 T 22

  23. 23

  24. CsI Calorimeter Testing: • Size • Source tests ( 137 Cs) • LED tests • PD tests • Preamp tests • Cosmic ray tests • Beam tests (6 x 6 array): X position 24 ADC

  25. Mechanical structure A 1/60 prototype Status: • Assembly will start soon. Should be completed by end of year. • By the end of the year, all FED boards should be tested 25 and installed.

  26. TOF Crucial for particle ID • Barrel – 50mm x 60mm x 2320 mm (inner layer). – BC408 – 2 layers 88x2 • Endcap – 48 fan shaped pieces – each end. – BC404 • PMT: Hamamatsu R5942 26

  27. TOF Performance Time resolution 1-layer  (intrinsic): Capability of K/ π separation Belle: 70 to 80 ps  Beam tests: < 90 ps  Simulation: < 90 ps   Time resolution of two layers is 100ps to 110ps for kaon and pions. K/ π separation: 2 σ  separation up to 0.9 GeV/c. 27

  28. Beam tests of TOF module  TOF module includes: scintillator, PMTs, preamps, 18m cable, VME readout board of FEE. Pion: 104±11ps proton: 70±2ps Electron: 94±3ps Time resolution from beam test of prototype (i ncluding scintillator, PMT, preamp, electronics, cable). Time difference of two TOF layers: no errors from reference time (T o ) or position. 28

  29. TOF Monitor System  Monitor the amplitude and time performance of each channel including PMTs and electronics.  U. Tokyo responsible for PMT testing in magnet  Being designed by University of Hawaii. Just approved by DOE: 3/1/2006 Electronic switch Fiber TOF endcap 48 fibers bundles TOF endcap 48 fibers Light splitter Laser TOF barrel 176 fibers TOF barrel 176 fibers fiber PMT connector TDC start Wrapped with ADC gate fiber steel tube Fiber PMT TOF barrel PMT 29

  30. Superconducting Magnet Coil: single layer solenoid Cooling mode: two phase helium force flow Superconductor: Al stabilized NbTi/Cu C ryost at Inner radius 1. 375m Winding: inner winding O ut er radi us 1. 7m Cold mass support: tension rod L engt h 3. 91m Thermal shield: LN 2 shield, MLI C oi l Flux return: barrel/end yoke, pole tip M ean radi us 1. 482m L engt h 3. 52m C abl e di m ensi on 3. 7m m *20m m Electrical parameters C ent ral f i el d 1. 0T N om i nal current 3650A Induct ance 2H St ored energy 10M J C ol d m ass 3. 6t on T ot al W ei ght 15t on R adi at i on t hi ckness 2X 0 30

  31. BESIII Magnet Progress wiring Thermal insulation assembly installation transportation 31

  32. Field mapping Computer controlled 3D mapping machine is under development. Field measuring accuracy < 0.25%. Measure ~90000 points with 0.5 mm position accuracy. Status: • Complete cooling test of the magnet before summer. Mapping device • Complete the field mapping together with SCQ before Dec. 31, 2006. 32

  33. Muon Chamber Barrel + EndCap; RPC as μ detector; Barrel : 9 layers EndCap: 8 layers One dimension read-out strips; 33

  34. RPCs • Electrodes made from a special type of phenolic paper laminate on bakelite. • Have good surface quality (~ 200nm). • Extensive testing and long term reliability testing done. • Have high efficiency, low counting rate and dark current, and good long-term stability . 34

  35. (RPC module) • Total of 64 endcap modules, 72 barrel modules; • Gas: Ar:C2H2F4:Iso_Butane = 50:42:8 • HV voltage: 8000V; • One module contains two RPC layers and one readout layer. 35

  36. All RPC production, assembly, testing, and installation completed. 36

  37. Test Result after installation - endcap Average strip efficiency: 0.97 Spatial resolution: 16.6mm Mean of 64 endcap RPC = 0.95 37

  38. μ / π Identification Efficiency Using Muc Info only From Simulation % 91.2 μ efficiency 90.3 87.6 18.9 12.6 π fake rate 15.0 6.24 9.0 6.0 12.0 9.0 5.5 GeV/c Design Goal Ratio of π decay to μ before entering Muc 38

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend