An Aggressive Plan fully Committed and Tailored to PR Needs By: - - PowerPoint PPT Presentation
An Aggressive Plan fully Committed and Tailored to PR Needs By: - - PowerPoint PPT Presentation
Highway Reconstruction Program An Aggressive Plan fully Committed and Tailored to PR Needs By: Ariel Prez, P.E., M.E. April 29, 2019 Jan 26, 2017 Introduction Current Challenges Our Top Priorities Key Infrastructure
Introduction Current Challenges Our Top Priorities Key Infrastructure Initiatives
- Abriendo Caminos
PEMOC (CAPEX 75) High Quality Pavement Repair FHWA Reconstruction Program
- Other Initiatives
CDBG-DR & Congestion Management
Final Remarks
2
HTA roads in worst state of disrepair in its
history
Expediting the reconstruction efforts Construction Industry Growing Pains Expenditures of Obligated Federal Funds had
been delayed
STIP Approval – Planning Consistency Limited resources
3
4
Disbursements (in millions of $)
693 177 176 584 631 808 757 880
2016 2018 2020 2011 2003 2000 1998 1996 1997 1999 2014 2012 2010 2008 2006 2004 2002 2017 2005 2007 2013 2021 2009 2015 2019 2001
348 446 421 222 165 617 517 367 277 889 403 424 247 218 571 671 840 743 Year 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 CIP 517 617 840 880 889 743 757 808 671 571 367 277 218 424 631 403 584 421 222 176 177 165 247 693 446 348
[1] HTA developed a long-term, steady-state CIP for its highway infrastructure it believes it needs to keep the highway system in a state of good repair and critical to HTA receiving full federal funds. To develop these funding levels, HTA used available data on asset condition, lifecycle, and historical costs. Following its initial analysis, HTA hired an outside engineering consultant to conduct a validation the CIP. After integrating the results of the external study, PRHTA estimates a steady-state CIP of $261.8M per year.
HTA’s estimated steady state CIP is $261.8M in hard costs per year [1]
5 * Includes both construction and soft costs and does NOT include CIP for Transit Asset
130 86 33 13 Bridges Safety Pavement Traffic signalling
Current Average Allocation for Pavement = $45MM per year
- Only in the next 5
years, it is expected a disbursement projection totaling $1,684MM on regular projects (Mostly in reconstruction activities)
- From ER program,
additional disbursements in the
- rder of $700MM are
anticipated in the same period of time.
$- $100,000,000 $200,000,000 $300,000,000 $400,000,000 $500,000,000 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28
Allocated Hard Costs Unallocated Hard Costs Soft Costs
Projected Disbursements (Excluding EFLHD)
7
Recent experience in construction cost increases:
- In May 23, 2018, based on limited information, FHWA
projects were estimated to increase from $146.5 M to $184 M (26% increase)
- After having awarding about half the bids, the
estimated increase is from$146.5 M to $214 M (46% increase)
- This increase is mostly attributable to hurricane Maria
market effect
8
Innovation in Project Delivery – Use of Abbreviated PS&Es, Georeferenced videos for roadway condition assessments. Quality Assurance Program (Design) Design Build SOPs for Small Projects – Future consultation to Transportation Innovative Council – TIC) Update of Design Manual, Standard Specs and Standard Drawings Strategic Highway Safety Plan Transportation Asset Management Plan
10
- FHWA MOU (Financial, Billing, Electronic Bidding process)
- Strengthening In-house offices with external resources (i.e.,
Procurement, Environmental, Design)
- Outsourcing O&M of Toll Roads
- Use of local funds for Pre-construction efforts, while
maximizing FHWA funds to cover construction costs
- Improving Cash Flow of Contractors/Suppliers
- Project bundling to attract contractors from other jurisdictions
- Strategic Partners
11
PRHTA EFLHD AGC PRIFA DTOP LTAP FHWA
Safety + Reconstruction Infrastructure - Our Top Priorities
Jan 26, 2017
13
Bridge Preservation / Rehab / Replacement Program Pavement Preservation / Reconstruction Highway Safety
90% (approx.) of the PRHTA’s projects to be procured in the next 6 years are focused on preservation / reconstruction and improving safety of our highway infrastructure
14
PRHTA is managing an investment
- f
$652MM in Reconstruction, where 80% or more are related to Pavement Preservation, Maintenance and/or reconstruction
PEMOC $75MM FHWA Reconstruction $250MM Pavement Repair $327MM
ABRIENDO CAMINOS PROGRAM
Key Infrastructure Initiatives ABRIENDO CAMINOS
Jan 26, 2017
16
8/8/2019
High Quality Pavement Repair
Focused
- n
preservation/maintenance
- f
highly deteriorated pavements using higher standards and quality control.
Divided in 4 phases:
17
8/8/2019
Phase Funding Priorities I $80,000,000 Priorities to Toll roads and primary system. About 30%
- f projects in Secondary and Tertiary System. Engaging
mostly Asphalt Pavement II $80,000,000 Higher priority to Secondary and Tertiary system. Will Consider concrete pavement, pavement marking, and retroreflective pavement markers III $80,000,000 TBD – Based on current conditions and lessons learned IV $87,000,000 TBD – Based on current conditions and lessons learned
Damage assessment using georeferenced video. Repair work is
defined in Task Orders. Adjustments can be made during construction, based on contracted unit prices.
Training to Contractor and Inspector on contract specs. Use of PRHTA’s standard specifications for asphalt mix (use of
warm mix)
Set of standard details for cold milling Material testing program (lab and field) Field Inspections
18
8/8/2019
19
8/8/2019
Section Repair and Compaction Testing (Nuclear Method)
20
8/8/2019
21
8/8/2019
PR-6 (Bayamón) PR-417 (Aguada)
22
8/8/2019
PR-2 (Camuy) PR-2 (Mayaguez)
23
8/8/2019
PR-106 (Mayagüez) PR-941 (Gurabo)
24
8/8/2019
PR-111 (Utuado)
25
8/8/2019
PRHTA will be procuring $75MM (Phase II of High Quality
Pavement Repair - HQPR)
$5MM will be used for program/project management, data
gathering, design, construction management and inspection services.
PRIFA will assist PRHTA in procuring Phase II of HQPR Second Phase will include:
- Pothole Repair Contracts
- WTBP Contracts – including Potholes, Strips and Sections
- Sections Repair Contracts
- Pavement Marking Contracts
- Concrete Slab Replacement Contracts
26
27
8/8/2019
PEMOC and FHWA Reconstruction Program
Programa Estatal de Modernización de Carreteras (PEMOC)
- Main objective is the reconstruction of secondary and tertiary roadway
system.
- Work includes cold milling, resurfacing, drainage improvements, safety
devices, minor retaining walls, pavement marking and signing.
- 11 contracts islandwide with an investment of $75MM
FHWA Reconstruction Program
- Highway Safety Improvements and Pavement Reconstruction
- 75% or more of funding is allocated for National Highway System (NHS)
- Closely coordinated with Transportation Asset Management Plan
(TAMP).
- Includes bridge preservation, reconstruction and replacement
28
ER Program
Jan 26, 2017
Interstate
279 miles
National Highway System (NHS) Primary, Secondary and Tertiary System (No- NHS)
525 miles 4,039 miles 789 Damages 1,174 DDIRs
Category # # of
- f DDI
DDIR's 's Bridges 147 Lighting 7 Traffic Signal 199 Communications 18 Hwy Related 746 Signing / Safety 57 Grand Tot
- tal
1,17 1,174
Brid idges 12% 12% Li Ligh ghtin ing 1% 1% Traf affic ic Signal 17% 17% Com
- mmunicati
tion
- ns
1% 1% Hwy Hwy Rela lated 64% 64% Signin ing / Saf afety 5% 5%
FHWA Elegible Damages by Category
Eligible Costs by Category
Category DDI DDIR Es Estimate Bridge $86,887,112.86 Lighting $4,360,101.03 Hwy Related $280,925,435.34 Signing / Safety $43,295,326.29 Traffic Signal $20,485,321.40 Communication $3,226,650.00 Grand Tot
- tal
$439,179,9 ,946.92 Bridges 18% 18% Lig Lighting 1% 1% Hwy wy Rel elated 65% 65% Sig Signage & Sa Safety 10% 10% Traffi fic Sig Signals 5% 5% Communicati
- ns
- ns…
- Based on DDIR estimate, which is considered underestimated. Updated
estimate around $836MM.
Item Funding
PRHTA Obligated Funds $ 163,000,000 PRHTA's Future Obligations $ 129,520,000 EFLHD MOU 1 $ 8,100,000 EFLHD MOU 2 $ 535,480,000 Subtotal $ 836,100,000
Item Allocation
ER Program Allocations (As of April 2019) $ 272,500,000 Subtotal $ 563,600,000
Other Key Initiatives Non-Reconstruction Initiatives
Jan 26, 2017
CDBG-DR Opportunities (Up to 2.4Billions requested) Intersection/Interchanges under Congestion Management
Program ($249MM)
37
Item Description of Intersection ** Total Cost, $ 1 PR-1 & PR-52 $ 17,500,000.00 2 PR-2 & PR-22 $ 24,000,000.00 3 PR-22 & PR-18 $ 45,000,000.00 4 PR-17 & PR-18 $ 58,000,000.00 5 Paraná & PR-177 $ 4,500,000.00 6 PR-176 & PR-1 $ 2,500,000.00 7 PR-52 & PR-199 $ 3,200,000.00 8 PR-2 & PR-114 $ 19,000,000.00 9 PR-165 & PR-28 $ 18,000,000.00
Potential Infra-Grant
** Preliminary planned under Design-Build Approach
Maintaining our highway system in State of Good
Repair while improving safety as the main
- bjective
Highest investment in highway reconstruction in
recent years
Future investment in pavement rehab projects to
reach $130MM annually.
80% of Reconstruction Costs are pavement rehab
related.
Maintaining
the highest standard in maintenance, preservation, and reconstruction of pavements is imperative.
39