AMLIN AREA PLAN PHASE 1 FINDINGS OCTOBER 22, 2019 INITIAL CONCEPT - - PowerPoint PPT Presentation

amlin area plan
SMART_READER_LITE
LIVE PREVIEW

AMLIN AREA PLAN PHASE 1 FINDINGS OCTOBER 22, 2019 INITIAL CONCEPT - - PowerPoint PPT Presentation

AMLIN AREA PLAN PHASE 1 FINDINGS OCTOBER 22, 2019 INITIAL CONCEPT REVIEW AGENDA PROJECT COORDINATION 1 Who Weve Talked to EXISTING CONDITIONS 2 Resident Concerns Stormwater Observations Stormwater Infrastructure and Encroachment Issues


slide-1
SLIDE 1

OCTOBER 22, 2019

AMLIN AREA PLAN

PHASE 1 FINDINGS

slide-2
SLIDE 2

PROJECT COORDINATION

Who We’ve Talked to

EXISTING CONDITIONS

Resident Concerns Stormwater Observations Stormwater Infrastructure and Encroachment Issues Railroad Alley Ownership Traffjc and Mobility Analysis

INITIAL RECOMMENDATIONS

Rings Road Alley Rings Road and Cosgray Road Intersection Short-term Opportunities

1 2 3

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

INITIAL CONCEPT REVIEW AGENDA

2

slide-3
SLIDE 3
  • 1. PROJECT COORDINATION

AMLIN AREA PLAN

slide-4
SLIDE 4

CITY OF DUBLIN

Plans and Reports Roadway Information

FRANKLIN COUNTY ENGINEER’S OFFICE

Historical Drainage Information Drainage / Ditch Petition Transportation Information

FRANKLIN COUNTY SANITARY ENGINEER

On-Site Septic Information (Complaints)

MORPC

Online Research

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

WHO WE HAVE TALKED TO

4

slide-5
SLIDE 5
  • 2. EXISTING CONDITIONS

AMLIN AREA PLAN

slide-6
SLIDE 6

Rings Road east of the railroad tracks. The Rings and Cosgray intersection.

EXISTING CONDITIONS

N 400 800

RINGS RD CHURCHMAN RD COSGRAY RD PLEASANT RUN BLVD M A R M A I O N D R EDEN BRIDGE DR

PARK IMPROVEMENTS DRAINAGE ISSUES PROPERTY UPKEEP STANDARDS

THE ALLEY RINGS RD

DRAINAGE SYSTEM NOT WORKING

1ST AVE 2ND AVE 3RD AVE I N C H C A P E L N F O R E L A N D L N

CITY OF DUBLIN CITY OF DUBLIN WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RESIDENT CONCERNS

6

slide-7
SLIDE 7

EXISTING CONDITIONS

Drainage tiles connecting to Ballantrae. This diagram depicts the concerns of residents pertaining to pooling water and drainage issues. Specifjcs on problem areas would need to be confjrmed with further investigation. Some of the drainage tiles need cleaning and upkeep.

N 200 400

RINGS RD CHURCHMAN RD RINGS RD

PROPERTIES WITH DRAINAGE ISSUES

1ST AVE 2ND AVE 3RD AVE

POOLING WATER DRAINAGE SYSTEM NOT WORKING

THE ALLEY I N C H C A P E L N F O R E L A N D L N

WASHINGTON TOWNSHIP CITY OF DUBLIN POOLING WATER

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RESIDENT CONCERNS STORMWATER

7

slide-8
SLIDE 8

N 160’ 320’

STORMWATER SYSTEM RIGHT OF WAY

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

STORMWATER INFRASTRUCTURE AND ENCROACHMENT ISSUES

8

slide-9
SLIDE 9

N 160’ 320’

STORMWATER SYSTEM RIGHT OF WAY ENCROACHMENT

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

STORMWATER INFRASTRUCTURE AND ENCROACHMENT ISSUES

9

slide-10
SLIDE 10

Approximate location of Railroad Ownership versus private property

PROPERTY BOUNDARY RAILROAD RIGHT OF WAY

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RAILROAD ALLEY OWNERSHIP

10

slide-11
SLIDE 11

The alleys ofg of Rings Road provide connections and parking. Rings Road lacks a continuous sidewalk network.

TRAFFIC AND MOBILITY ANALYSIS

N 400 800

RINGS RD CHURCHMAN RD PLEASANT RUN BLVD M A R M A I O N D R 1ST AVE 2ND AVE EDEN BRIDGE DR 3RD AVE THE ALLEY RINGS RD

POSSIBLE ALLEY CONNECTION OPPORTUNITY FOR IMPROVED MOBILITY

COSGRAY RD

EXISTING LOCAL TRAIL TRAFFIC AND SAFETY CONCERNS

I N C H C A P E L N F O R E L A N D L N

CITY OF DUBLIN CITY OF DUBLIN WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

TRAFFIC AND MOBILITY ANALYSIS

11

slide-12
SLIDE 12
  • 3. INITIAL RECOMMENDATIONS

AMLIN AREA PLAN

slide-13
SLIDE 13

N 400 800

CHURCHMAN RD COSGRAY RD M A R M A I O N D R THE ALLEY RINGS RD

Lack of sidewalks disrupts the pedestrian connection; impacts safety. Above ground utilities disrupt the natural streetscape. Existing structures encroach into the right of way on Rings Road.

NO SIDEWALK INFRASTRUCTURE EXISTING UTILITIES NEED STREET IMPROVEMENTS ENCROACHMENT ISSUES PROPERTIES WITH DRAINAGE ISSUES

1ST AVE 2ND AVE 3RD AVE F O R E L A N D L N I N C H C A P E L N

WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP CITY OF DUBLIN CITY OF DUBLIN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD CURRENT ISSUES

13

slide-14
SLIDE 14

NO SIDEWALK INFRASTRUCTURE EXISTING UTILITIES NEED STREET IMPROVEMENTS ENCROACHMENT ISSUES PROPERTIES WITH DRAINAGE ISSUES

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD EXISTING CONDITIONS

14

slide-15
SLIDE 15

Existing conditions of Rings Road SECTION PLAN 20’ 60’ R.O.W. 3.5’ 3.5’

EXISTING SHOULDER EXISTING ROADWAY EXISTING DRAINAGE DITCH AND STORM INLET EXISTING SHOULDER EXISTING DRAINAGE DITCH AND STORM INLET ON-LOT SEPTIC CONNECTIONS EXISTING STORM PIPE

SITE PHOTOS

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD EXISTING CONDITIONS

EXISTING STORM INLET ROAD SHOULDER EXITING UTILITY POLE EXISTING UTILITY POLE ROAD SHOULDER

15

slide-16
SLIDE 16

20’ 3.5’ 3.5’

EXISTING SHOULDER EXISTING SHOULDER ADDED STORM INLETS TO ADDRESS YARD FLOODING STREET TREE ADDED STORM INLETS TO ADDRESS YARD FLOODING

60’ R.O.W.

EXISTING STORM PIPE

SECTION PLAN

COST ANALYSIS

  • Cleaned and scoped storm system.
  • Possible re-grading to improve drainage fmow
  • Low-height street trees are added where there

is room.

  • Solutions will be less expensive, but lack

signifjcant impact in addressing community concerns. Additional Street Trees: 20-30 Trees $10,000 - $15,000 CCTV of existing stormwater system: $8,000 - $15,000 Grading work cost would require further study in specifjc areas where new grading is needed and is achievable.

ON-LOT SEPTIC CONNECTIONS

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD PROPOSED LOW IMPACT

EXISTING MANHOLE ROAD SHOULDER PROPOSED PLANTING EXITING UTILITY POLE EXISTING UTILITY POLE PROPOSED LOW HEIGHT PLANTING ROAD SHOULDER

16

slide-17
SLIDE 17

CURB ADJACENT SIDEWALK PROPOSED PLANTING EXITING UTILITY POLE

20’ 4’ 5’

SIDEWALK (4’) CURB ADJACENT SIDEWALK RECONSTRUCTED ROADWAY W/ CURB AND GUTTER ENHANCED DRAINAGE DITCH AND ADDED STORM INLETS NEW STORM PIPE

60’ R.O.W.

EXISTING STORM MANHOLE

SECTION PLAN

COST ANALYSIS Approximate Project Cost: $700 / LF ~1,300 Feet Including replacement of most of the existing drainage system; not including engineering/ design, permit, easement acquisition and construction phase services.

  • Curb and gutter added
  • Catch basins, new stormwater pipe
  • Pedestrian only sidewalk added
  • Low-height street trees

ON-LOT SEPTIC CONNECTIONS NEW STORM PIPE

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD PROPOSED MEDIUM IMPACT

EXISTING UTILITY POLE PROPOSED LOW HEIGHT PLANTING CURB ADJACENT SIDEWALK

17

slide-18
SLIDE 18

CURB AND GUTTER CURB ADJACENT SIDEWALK ENCROACHING BUILDING SIDEWALK NEW STORM MANHOLE

SECTION PLAN

COST ANALYSIS Approximate Project Cost: $1,500 / LF ~1,300 Feet Including burying existing overhead utilities and replacement of the existing drainage system; not including engineering/design, permit, easement acquisition and construction phase services.

  • Complete road reconstruction includes

lowering road height to help with drainage.

  • Curb and gutter added
  • Catch basins, new stormwater pipe
  • Tree lawn, new street lights, and sidewalk

added to both sides.

  • Utilities moved below grade.

Lowering the road is only feasible if a suitable drainage outlet exists at a low enough elevation. Further investigation is needed to ensure feasibility.

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD PROPOSED HIGH IMPACT VERSION 1

TREE LAWN (4’) SIDEWALK (5’) SIDEWALK (5’) YARDS SLOPE TO ROADWAY UNDERGROUND UTILITIES SIDEWALK (5’) NEW DECORATIVE STREET LIGHT RECONSTRUCTED ROADWAY W/ CURB AND GUTTER NEW STORM PIPE

60’ R.O.W. 20’ 4’ 5’ 4’ 5’

ON-LOT SEPTIC CONNECTIONS NEW STREET TREE

18

slide-19
SLIDE 19

CURB AND GUTTER ENCROACHING BUILDING MULTIPURPOSE PATH NEW STORM MANHOLE

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS ROAD PROPOSED HIGH IMPACT VERSION 2

TREE LAWN (4’) SIDEWALK (5’) MULTIPURPOSE PATH SIDEWALK (5’) NEW STORM PIPE

60’ R.O.W. 20’ 4’ 8’ 4’ 5’ SECTION PLAN

COST ANALYSIS Approximate Project Cost: $1,500 / LF ~1,300 Feet Including burying existing overhead utilities and replacement of the existing drainage system; not including engineering/design, permit, easement acquisition and construction phase services.

  • Difgerence from version 1 is that the sidewalk
  • n the north side of Rings Road is instead

a multi-purpose path for bicyclists and pedestrians. Lowering the road is only feasible if a suitable drainage outlet exists at a low enough elevation. Further investigation is needed to ensure feasibility.

NEW STREET TREE YARDS SLOPE TO ROADWAY UNDERGROUND UTILITIES NEW DECORATIVE STREET LIGHT ON-LOT SEPTIC CONNECTIONS RECONSTRUCTED ROADWAY W/ CURB AND GUTTER

19

slide-20
SLIDE 20

N 400 800

CHURCHMAN RD COSGRAY RD M A R M A I O N D R

WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP

THE ALLEY RINGS RD

Current trail and alley connection can be enhanced. Alleys all used as connector streets may not be necessary.

TRAIL CONNECTION ALLEY/RINGS RD CONNECTORS

1ST AVE 2ND AVE 3RD AVE

RAIL ROAD RIGHT OF WAY PROPERTIES WITH DRAINAGE ISSUES

F O R E L A N D L N I N C H C A P E L N

CITY OF DUBLIN CITY OF DUBLIN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

ALLEY CURRENT ISSUES

20

slide-21
SLIDE 21

EXISTING SCREENING VEGETATION EXISTING ALLEY RESIDENTIAL DRIVE + GARAGE

SECTION PLAN

RESIDENTIAL DRIVE + GARAGE EXISTING SCREENING VEGETATION

Existing conditions of the alley. SITE PHOTOS

RIGHT OF WAY VARIES FROM 15’ TO 18’

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

ALLEY EXISTING CONDITIONS

9’ 15’ R.O.W.

21

slide-22
SLIDE 22

SECTION PLAN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

ALLEY PROPOSED CONDITIONS

WIDENED ALLEY YARDS DRAIN TO ROAD CONVEYANCE STORM RUNOFF CONVEYANCE WIDENED ALLEY WITH RUNOFF CONVEYANCE PITCH YARD TO DRAINAGE

12’ 15’ R.O.W.

COST ANALYSIS Approximate Project Cost: $500 / LF ~1,420 Feet of Alley Including alley reconstruction drainage system; not including engineering/design, permit, easement acquisition and construction phase services.

  • Reconstructed alley to ensure consistent width

and alignment.

  • Allows for emergency safety access to

structures in rear of property

  • Drainage system installed in center of alley to

aid in draining the rear of properties.

22

slide-23
SLIDE 23

VACATED PORTION OF ALLEY ALLEY ACCESS FROM RINGS RD MAINTAIN DRIVEWAY ACCESS

Future vacated alley along 2nd Avenue. The alley with access to Rings Road at Friezell Avenue. The alley at 3rd Avenue.

CIRCULATION FOR TRAIL AND FIRE ACCESS

N 100 200

T H E A L L E Y

R I N G S R D 1 S T A V E 2 N D A V E 3 R D A V E

CITY OF DUBLIN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

ALLEY VACATED ALLEYWAYS

23

slide-24
SLIDE 24

Example of a new asphalt alley path

RUNOFF ENTERS BALLANTRAE ALLEY RUNOFF CONVEYANCE YARD RUN- OFF FLOW T H E A L L E Y

R I N G S R D 1 S T A V E 2 N D A V E 3 R D A V E

CITY OF DUBLIN

N 100 200 AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

ALLEY RUNOFF CONVEYANCE

  • Alley drainage system will aide in the drainage

issues in the rear of the properties on north side of Rings Road.

  • Plan for drainage system includes connecting

into the Ballantrae inlet and detention pond.

  • This would require approval from the

City of Dublin.

24

slide-25
SLIDE 25

The trail coming from Ballantrae into Amlin

TRAIL MOBILITY AND CONNECTIONS

N 400 800

RINGS RD CHURCHMAN RD COSGRAY RD PLEASANT RUN BLVD M A R M A I O N D R I N C H C A P E L N EDEN BRIDGE DR

EXISTING LOCAL TRAIL ALLEY TRAIL POTENTIAL TRAIL CONNECTION POTENTIAL SW CONNECTION

1ST AVE 2ND AVE 3RD AVE F O R E L A N D L N

WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP CITY OF DUBLIN CITY OF DUBLIN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

TRAIL MOBILITY

  • Alley path would serve as the primary bike and

pedestrian connection for Amlin.

  • The path would connect with the trail from

Ballantrae that ends in Amlin behind the former Pizza shop.

  • The alley path has potential to make additional

connections to the east via the sidewalk network at Churchman Road or the planned bike connections south of Rings Road as a part

  • f the future trail planning done by the City of

Dublin.

25

slide-26
SLIDE 26

RINGS AND COSGRAY INTERSECTION

The ofgset intersections at Rings Road and Cosgray Road

N 400 800

HIGH SPEEDS

RINGS RD CHURCHMAN RD COSGRAY RD PLEASANT RUN BLVD M A R M A I O N D R I N C H C A P E L N EDEN BRIDGE DR 1ST AVE 2ND AVE 3RD AVE F O R E L A N D L N

WASHINGTON TOWNSHIP WASHINGTON TOWNSHIP CITY OF DUBLIN CITY OF DUBLIN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

RINGS AND COSGRAY ROADS CURRENT ISSUES

  • Intersection at Rings and Cosgray has been a

concern of residents in the area recently due to increased traffjc resulting from the nearby development.

  • Concerns included higher traffjc volumes,

higher speeds, and perception of a lack of safety.

26

slide-27
SLIDE 27

N 200 400

POTENTIAL UTILITY IMPACTS POTENTIAL UTILITY IMPACTS POTENTIAL UTILITY IMPACTS POTENTIAL UTILITY IMPACTS POTENTIAL UTILITY IMPACTS ROAD CROSSINGS POTENTIAL FOR LANDSCAPING OR SMALL MONUMENT CURVE DESIGNED FOR 35 MPH. ADVANCED WARNING SIGNS RECOMMENDED.

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

CONCEPTUAL RENDERING OF RINGS AND COSGRAY ROADS ROUNDABOUT SOLUTION

COST ANALYSIS Approximate Project Cost: $2 Million Not including engineering/design, permit, easement/land acquisition and construction phase services.

  • Roundabout is a more compact solution than a

signalized 4-way intersection.

  • Roundabout would increase the effjciency and

safety of this intersection while providing traffjc calming.

  • The alignment of the roundabout was careful

to minimize the impact on private properties, however, two residential properties east of Cosgray would be impacted.

  • The diagram at right is a depiction of a possible

roundabout design for the intersection. This design has not been approved and should be studied more in the future.

27

slide-28
SLIDE 28

RIVER BIRCH ZELKOVA

STREET TREES

  • Need to be low in height when mature due to overhead utilities.
  • Possible Tree Species:
  • Trident Maple
  • River Birch
  • Zelkova
  • Approximate Cost: $10,000 - $15,000

20-30 Trees

COMMUNITY SIGNS

  • New signage to better create an identity
  • Gateway neighborhood/community signs
  • Allowance: Approx. $5,000

TREE REMOVAL AND LANDSCAPING CLEAN-UP

  • In order to conduct the tree removal as discussed, the township

would need to gather signed waivers from private property

  • wners

TRIDENT MAPLE AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

SHORT-TERM IMPROVEMENTS

28

slide-29
SLIDE 29

REVIEW & REFINEMENT OF RECOMMENDATIONS SELECTION OF PREFERRED STRATEGY REFINED COST ESTIMATES DEVELOP ACTION STRATEGY FINALIZE PLAN

AMLIN AREA PLAN WASHINGTON TOWNSHIP, OHIO

NEXT STEPS

29