- G. Lolov
3 Month Progress Update G. Lolov TSD Meeting 13 December 2018 - - PowerPoint PPT Presentation
3 Month Progress Update G. Lolov TSD Meeting 13 December 2018 - - PowerPoint PPT Presentation
3 Month Progress Update G. Lolov TSD Meeting 13 December 2018 NOvA Installation Issues Recap Issue with push pull rod, plunger was hitting the stop Hanger couldnt align correctly with draw bar on module Push pull rod was bent 2
NOvA Installation Issues Recap
George Lolov | 3 Month Progress Update 2
- Issue with push pull rod, plunger was hitting the stop
- Hanger couldn’t align correctly with draw bar on module
- Push pull rod was bent
12/13/2018
3
Target Carrier Ramp
- 2”x1” 80/20 for frame, 2”x2” 80/20 for supports
- Angled at 3.34349° like the target will be
- Side Guards for guidance
- 120 lbs estimated, can hang on wall
Supports Side Guards
George Lolov | 3 Month Progress Update 12/13/2018
Hanger Positioner
4
- Plugs thread into hangers
- 80/20 2”x2” bars slot into plugs
- Optional set screw to fix bars
Plug Bars slot in Set Screw
George Lolov | 3 Month Progress Update 12/13/2018
Installation Procedure
5
1) Place target carrier on ramp
George Lolov | 3 Month Progress Update 12/13/2018
Installation Procedure
6
2) Adjust hangers using a level so that they are parallel to ground
George Lolov | 3 Month Progress Update 12/13/2018
7
Installation Procedure
3) Grease plugs and thread in, then slot in the bar assembly to check if hanger adjustment is correct
George Lolov | 3 Month Progress Update 12/13/2018
Fully Assembled View
12/13/2018 8 George Lolov | 3 Month Progress Update
Ramp Hanger Positioner Mock Carrier
Pre-Installation Checklist
9 George Lolov | 3 Month Progress Update 12/13/2018
Stripline Shielding Blocks Fastener Failure
12/13/2018 10
- Stud Bolts experienced fracture during preload
- Torsional failure due to galling
George Lolov | 3 Month Progress Update
12/13/2018 11
Stripline Shielding Blocks Fastener Failure
Conclusion: Use ARP Fastener Lubricant to prevent galling
George Lolov | 3 Month Progress Update
Stripline Airflow Testing
12/13/2018 12
- Goal: Increase cooling on stripline to allow for move up to 1 MW
Cooling Curve Test Pressure Test
- Heated up coupon, turned on fans
- Derived convection coefficient
George Lolov | 3 Month Progress Update
New Diverter Design: Inlet
12/13/2018 13
- 4 sheet metal sheets curved into quarter-ellipses
- Inlet area doubled from previous design
Old Design New Design
George Lolov | 3 Month Progress Update
12/13/2018 14
New Diverter Design: Outlet
- Made openings 2x as large
since inlet area doubled
- Centered openings
between stripline flags
George Lolov | 3 Month Progress Update
Full Diverter Assembly
12/13/2018 15
Outlet Inlet Mounting Bracket
George Lolov | 3 Month Progress Update
BnB Mechanical Model
12/13/2018 16
- One of the coax cables for the BPMs failed
- Research more radiation resistant coax cables/connectors
- Kapton
- Ceramics
- Design a mechanical model to make replacing cables
easier
George Lolov | 3 Month Progress Update
Coax Cable Assembly
12/13/2018 17
Coax Connectors Guide Plates Coax Cable Assemblies
George Lolov | 3 Month Progress Update
Coax Cable Assembly
12/13/2018 18
Coax Cables Hex Adapters SS Pipes
George Lolov | 3 Month Progress Update
12/13/2018 19
Coax Cable Assembly
Pipe Bushings Coax Cables
George Lolov | 3 Month Progress Update
Possible Issues
12/13/2018 20
- A lot of clutter
- Magnet will need
to be moved back
George Lolov | 3 Month Progress Update
- Mu2e Proposal for Emissivity/Creep Target Testing
- Electroless Nickel Coating Characterization on Horn
- Trained on CNC TiG Welding Machine
- USPAS on High Power Targets in January
Future Projects
12/13/2018 21 George Lolov | 3 Month Progress Update