3 month progress update
play

3 Month Progress Update G. Lolov TSD Meeting 13 December 2018 - PowerPoint PPT Presentation

3 Month Progress Update G. Lolov TSD Meeting 13 December 2018 NOvA Installation Issues Recap Issue with push pull rod, plunger was hitting the stop Hanger couldnt align correctly with draw bar on module Push pull rod was bent 2


  1. 3 Month Progress Update G. Lolov TSD Meeting 13 December 2018

  2. NOvA Installation Issues Recap • Issue with push pull rod, plunger was hitting the stop • Hanger couldn’t align correctly with draw bar on module • Push pull rod was bent 2 12/13/2018 George Lolov | 3 Month Progress Update

  3. Target Carrier Ramp • 2”x1” 80/20 for frame, 2”x2” 80/20 for supports • Angled at 3.34349 ° like the target will be • Side Guards for guidance • 120 lbs estimated, can hang on wall Side Guards Supports 3 12/13/2018 George Lolov | 3 Month Progress Update

  4. Hanger Positioner • Plugs thread into hangers • 80/20 2”x2” bars slot into plugs • Optional set screw to fix bars Bars slot in Plug Set Screw 4 12/13/2018 George Lolov | 3 Month Progress Update

  5. Installation Procedure 1) Place target carrier on ramp 5 12/13/2018 George Lolov | 3 Month Progress Update

  6. Installation Procedure 2) Adjust hangers using a level so that they are parallel to ground 6 12/13/2018 George Lolov | 3 Month Progress Update

  7. Installation Procedure 3) Grease plugs and thread in, then slot in the bar assembly to check if hanger adjustment is correct 7 12/13/2018 George Lolov | 3 Month Progress Update

  8. Fully Assembled View Hanger Positioner Mock Carrier Ramp 8 12/13/2018 George Lolov | 3 Month Progress Update

  9. Pre-Installation Checklist 9 12/13/2018 George Lolov | 3 Month Progress Update

  10. Stripline Shielding Blocks Fastener Failure • Stud Bolts experienced fracture during preload • Torsional failure due to galling 10 12/13/2018 George Lolov | 3 Month Progress Update

  11. Stripline Shielding Blocks Fastener Failure Conclusion: Use ARP Fastener Lubricant to prevent galling 11 12/13/2018 George Lolov | 3 Month Progress Update

  12. Stripline Airflow Testing • Goal: Increase cooling on stripline to allow for move up to 1 MW Cooling Curve Test Pressure Test • Heated up coupon, turned on fans • Derived convection coefficient 12 12/13/2018 George Lolov | 3 Month Progress Update

  13. New Diverter Design: Inlet • 4 sheet metal sheets curved into quarter-ellipses • Inlet area doubled from previous design Old Design New Design 13 12/13/2018 George Lolov | 3 Month Progress Update

  14. New Diverter Design: Outlet • Made openings 2x as large since inlet area doubled • Centered openings between stripline flags 14 12/13/2018 George Lolov | 3 Month Progress Update

  15. Full Diverter Assembly Inlet Outlet Mounting Bracket 15 12/13/2018 George Lolov | 3 Month Progress Update

  16. BnB Mechanical Model • One of the coax cables for the BPMs failed • Research more radiation resistant coax cables/connectors • Kapton • Ceramics • Design a mechanical model to make replacing cables easier 16 12/13/2018 George Lolov | 3 Month Progress Update

  17. Coax Cable Assembly Coax Cable Assemblies Coax Connectors Guide Plates 17 12/13/2018 George Lolov | 3 Month Progress Update

  18. Coax Cable Assembly Coax Cables SS Pipes Hex Adapters 18 12/13/2018 George Lolov | 3 Month Progress Update

  19. Coax Cable Assembly Coax Cables Pipe Bushings 19 12/13/2018 George Lolov | 3 Month Progress Update

  20. Possible Issues • A lot of clutter • Magnet will need to be moved back 20 12/13/2018 George Lolov | 3 Month Progress Update

  21. Future Projects • Mu2e Proposal for Emissivity/Creep Target Testing • Electroless Nickel Coating Characterization on Horn • Trained on CNC TiG Welding Machine • USPAS on High Power Targets in January 21 12/13/2018 George Lolov | 3 Month Progress Update

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend