1 Assessing Risk in the Physical Build of a Network REANNZ - - PowerPoint PPT Presentation

1 assessing risk in the physical build of a network
SMART_READER_LITE
LIVE PREVIEW

1 Assessing Risk in the Physical Build of a Network REANNZ - - PowerPoint PPT Presentation

1 Assessing Risk in the Physical Build of a Network REANNZ lunchtime presentation 2019 WHAT REANNZ HAS LEARNED ABOUT ASSESSING RISK IN THE PHYSICAL NETWORK BUILD 2 Assessing Risk in the Physical Build of a Network REANNZ lunchtime


slide-1
SLIDE 1

1 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

slide-2
SLIDE 2

2 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

WHAT REANNZ HAS LEARNED ABOUT ASSESSING RISK IN THE PHYSICAL NETWORK BUILD

slide-3
SLIDE 3

4 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

DESIGNING FOR HIGH AVAILABILITY

  • Consider requirements
  • Consider budget
  • Avoid complexity
  • Understand single points of failure
  • Connectivity
  • Power
  • Hardware
slide-4
SLIDE 4

5 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

CONSIDER REQUIREMENTS

  • What does high availability mean to your business?
  • 99.99% is 52 minutes 36 seconds per year
  • 99.999% is 5 minutes 15 seconds per year
  • 24x7 or 8x5?
  • Scheduled maintenance time?
  • Network availability and service availability can be

different

slide-5
SLIDE 5

6 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

AN EXAMPLE OF REQUIREMENTS VS BUDGET

HLZ MUP WLG CHC LCN AVL PMR ROT DUD IVM AKL MTA

MORST RFP Design for NREN KAREN 2006

HLZ MUP WLG CHC LCN AVL PMR ROT DUD IVM AKL MTA NSH NPE CROF NSN

slide-6
SLIDE 6

7 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

AVOID COMPLEXITY

  • Chose which layer your network will be protected at
  • Consider soft failures as well as hard failures
  • How trusted is the technology?
  • While automated failover is usually the right answer there are

times where it’s not achievable

  • Where are spares located?
slide-7
SLIDE 7

8 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ 2006 - SOME OBVIOUS POINTS OF FAILURE & SOME NOT SO OBVIOUS

HLZ MUP WLG CHC LCN AVL PMR ROT DUD IVM AKL MTA NSH NPE CROF NSN

slide-8
SLIDE 8

9 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

PHYSICAL INFRASTRUCTURE MATTERS WHEN ASSESSING RISK

WLG CHC DUD NSN Blenheim Timaru Oamaru

slide-9
SLIDE 9

10 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

CONNECTIVITY EXAMPLES

  • Lincoln PoP
  • Napier-Gisborne
  • Cook Strait
slide-10
SLIDE 10

11 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

LINCOLN POP

slide-11
SLIDE 11

12 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

slide-12
SLIDE 12

13 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

slide-13
SLIDE 13

14 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

slide-14
SLIDE 14

15 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

HAWKES BAY – POVERTY BAY

slide-15
SLIDE 15

16 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

COOK STRAIT

slide-16
SLIDE 16

17 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

A FINAL OBSERVATION ABOUT FIBRE PATHS

slide-17
SLIDE 17

18 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ POP - POWER

  • Diverse power feeds on separate infrastructure
  • Backed by UPS
  • Backed by Generator
  • DC Power capable equipment
  • Correctly identified and delivered in a way that allows for

clear understanding of power usage

slide-18
SLIDE 18

19 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ MX480 DC SYSTEM

slide-19
SLIDE 19

20 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ MX480 AC SYSTEM

slide-20
SLIDE 20

21 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ AC CABLING

slide-21
SLIDE 21

22 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ POP - HARDWARE

  • Key sites have redundant
  • Routing engines (RE’s)
  • Switch fabrics (SCBE’s)
  • Power modules (PEM’s)
  • Line cards (FPC’s)
  • Interface cards (MIC’s)
  • As sites get smaller the routers have fewer redundant

components

slide-22
SLIDE 22

23 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ POP – MX480

slide-23
SLIDE 23

24 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ POP – MX80

slide-24
SLIDE 24

25 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

REANNZ POP – MX104

slide-25
SLIDE 25

26 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019

WHAT CAN YOU TAKE AWAY FROM WHAT REANNZ HAS LEARNED

  • Have a clear understanding of the goal
  • Understand the physical infrastructure beneath any services

purchased

  • Understand power delivery and how your equipment consumes power
  • Plan for components or systems to fail and think about how long it will

take to deploy spares – test this if possible

  • Understand and document your risks. Not everything can be mitigated
  • r should be. Cost vs Risk vs Requirements.
slide-26
SLIDE 26

27 Assessing Risk in the Physical Build of a Network – REANNZ lunchtime presentation 2019