(1) Adjudication! 3 October 2012 (2) Estidama! 4 October 2012 - - PDF document

1 adjudication
SMART_READER_LITE
LIVE PREVIEW

(1) Adjudication! 3 October 2012 (2) Estidama! 4 October 2012 - - PDF document

October 2012 Can Adjudication assist Abu Dhabi in achieving its Sustainability (Estidama) goals for the construction industry? Presentation by: Paul Straker FCInstCES, FRICS, FICE, MCIArb October 2012 1 October 2012 Credit to Others


slide-1
SLIDE 1

October 2012 1

Can Adjudication assist Abu Dhabi in achieving its Sustainability (Estidama) goals for the construction industry?

Presentation by: Paul Straker

FCInstCES, FRICS, FICE, MCIArb October 2012

October 2012

1

Credit to Others – Citations(?)

Kindly note that throughout this presentation; I cite

  • ther

eminent professionals, by cross reference to a bibliography at the end

  • f

the presentation notes(?).

October 2012

2

slide-2
SLIDE 2

October 2012 2

(1) Adjudication!

October 2012

3

(2) Estidama!

October 2012

4

slide-3
SLIDE 3

October 2012 3

(3) The ICES survey 2012

  • n Dispute Resolution!

October 2012

5

How do these 3 relate?

October 2012

6

slide-4
SLIDE 4

October 2012 4

My Hypothesis!

October 2012

7

“I assert that Adjudication can significantly assist Abu Dhabi in achieving its Estidama (sustainability) goals for the construction industry”

October 2012

8

slide-5
SLIDE 5

October 2012 5

The results of the ICES dispute resolution survey for Abu Dhabi 2012, support my assertion!

October 2012

9

HOW?

First some background information.

An Overview

  • f

Adjudication, Estidama & key findings from the dispute resolution survey.

October 2012

10

slide-6
SLIDE 6

October 2012 6

What is Adjudication?

  • “A process whereby the [neutral third party]

adjudicator who may not be a lawyer has to reach a decision on matters referred to him [by] the complaining party”. (1.1)

October 2012

11

Who is the Adjudicator?

  • Either

a single suitably qualified and experienced person / adjudicator.

  • Or

a dispute adjudication board (DAB), comprising of 3 suitably qualified adjudicators.

  • Appointed as a standing adjudicator/DAB at

commencement of the project; or on an ad- hoc basis; by the parties to the contract.

October 2012

12

slide-7
SLIDE 7

October 2012 7

What is an Adjudicator’s Decision?

  • After a dispute (rejection of a clearly defined

claim) has been referred to the adjudicator for his decision thereon.

  • The adjudicator, acting fairly and impartially, shall

adopt suitable procedures, to make his reasoned decision within a limited time (usually 3 months).

  • The adjudicator’s decision will be contractually

binding; unless and until revised in an amicable settlement or an arbitral award.

October 2012

13

What are the alternatives?

  • In Abu Dhabi Arbitration is the preferred

method of dispute resolution!

  • However,

the Abu Dhabi Commercial, Conciliation and Arbitration Center (ADCCAC) also offer Conciliation prior to Arbitration.(3.0)

  • Other

potential

  • ptions:

Negotiation; Mediation; Early Neutral Evaluation; Expert Determination; Litigation.

October 2012

14

slide-8
SLIDE 8

October 2012 8

Dispute Resolution Options

  • The following are the more commonly used

Alternative Dispute Resolution (ADR) methods.

  • Discussed in order, from simple inexpensive

methods, to the more complex, legalistic and increasingly expensive methods.

October 2012

15

Negotiation ADR Litigation

Negotiation

  • Theoretically gives the parties most control
  • ver the dispute resolution process.
  • Without the intervention of a third party: “…

typically consists of a sequence of proposals … and counter proposals … that continue until agreement is reached or negotiations break down …”. (1.2)

  • Negotiations often break down!

October 2012

16 WHY?

slide-9
SLIDE 9

October 2012 9

Negotiation cont’d

  • Here’s just one of many reasons; the human

ego and lack of negotiating skills:

– “There will be many times that others would gladly change their minds and agree with you except for one thing: … – … they have already made a definite commitment, … and cannot change position in good grace … – … Skillful persuaders know how to leave the door

  • pen so that others can escape from their

previous position without losing face .…”. (5.0)

October 2012

17

Mediation

  • The

least adversarial dispute resolution method; utilizing skilled persuaders!

  • “… the facilitation, by a third party, of a

negotiated agreement … in which the mediator does not decide the dispute, but facilitates communication and problem- solving by the parties”.(1.3)

  • The optimum solution?

October 2012

18

BUT WOULD IT WORK?

slide-10
SLIDE 10

October 2012 10

Conciliation

  • Utilizes similar techniques to Mediation, except:
  • Its more formalized; no meetings without both

parties present.

  • Results in a settlement proposal, made by the

conciliator.

  • Its a means of amicable settlement.
  • Non-binding on the parties; therefore open to

further dispute!

October 2012

19

Early Neutral Evaluation

  • Provided by an independent third party: “… an

early, frank and thoughtful evaluation of the relative positions of the parties …”;(1.4)

  • “… to enhance the prospects of a successful

negotiation …”;(1.4)

  • “… by offering a realistic view of what might

transpire if a case is fully prepared and tried”.

(1.4)

October 2012

20

slide-11
SLIDE 11

October 2012 11

Expert Determination

  • Used where the parties have appointed a third

party expert and: “… submit an issue for the determination of a third party …”.(1.5)

  • Its “used primarily in disputes of a technical

nature which require … an opinion on a specific issue or issues”.(1.6)

  • The parties may agree in advance, to be

contractually bound by the determination.

October 2012

21

Adjudication

  • Discussed

earlier: internationally proven; used by the Multilateral Development Banks (incl. the World Bank); on projects worldwide.

– FIDIC MDB Harmonised Construction Contract 2010; and throughout the FIDIC suite of contracts.

  • Limited cost, similar to conciliation (typically

between 0.2% - 0.5% of construction costs).

  • Reaches

an impartial and contractually binding decision; usually within 3 months.

October 2012

22

slide-12
SLIDE 12

October 2012 12

Adjudication cont’d

  • “The DB procedure amounts to serial adjudication

… over 90% of disputes referred to a DB will not go beyond that procedure into arbitration or litigation …”.(Dr. Robert Gaitskell QC CEng).(4.0)

  • Speedy resolution; thereby facilitating the works,

enhancing cash-flow and project delivery.

  • Disposes of the argument, before tensions build;

thereby preserving business relationships.

October 2012

23

Arbitration

  • An independent, impartial and finally binding,

private dispute resolution process; proven worldwide.

  • Typically the default method, after the client’s
  • wn dispute procedure in the UAE; and the

final method under FIDIC contracts.

  • Award

is enforceable in many countries

(pursuant to the New York Convention); therefore

may be attractive to foreign parties.

October 2012

24

slide-13
SLIDE 13

October 2012 13

Arbitration cont’d

  • Takes many months or 1 – 2 years to reach a

resolution.

  • Formal, adversarial, typically with only one

Arbitrator in UAE.

  • Heard

in private; but may still damage business relationships.

  • Similar cost to litigation; and substantially

more than any of the foregoing methods.

October 2012

25

Litigation

  • Not a form of ADR, but mentioned here to put

ADR in context.

  • Settlement of the dispute through the courts.
  • A judicial process that is finally binding;

subject to appeal.

  • May not be enforceable outside the UAE

jurisdiction; therefore may not be attractive to foreign parties.

October 2012

26

slide-14
SLIDE 14

October 2012 14

Litigation cont’d

  • May take many months or years conclude.
  • Costs similar to Arbitration.
  • Public hearing that may damage reputations.
  • Can result

in a breakdown of business relationships.

October 2012

27

Estidama!

October 2012

28

slide-15
SLIDE 15

October 2012 15

What is Estidama?

  • Estidama is Arabic for Sustainability!
  • But with a difference.
  • It is comprised of 4 fundamental pillars:

October 2012

29

Environment Economic Cultural Social

Integration at its core!

  • Estidama integrates the 4 pillars.
  • What are its expectations of the construction

industry?

  • “To achieve significant environmental, social,

economic and cultural benefits, while ensuring that the costs

  • f

the development are minimized.”(2.1)

October 2012

30

slide-16
SLIDE 16

October 2012 16

Pearl Rating System for Estidama

  • A green building rating system.
  • Launched by ABU Dhabi UPC in 2010.
  • Mandatory for all construction projects.

October 2012

31

Comprises

  • Mandatory and optional sustainability

requirements, to achieve:

– Minimum One Pearl Rating for all developments. – Minimum Two Pearl Rating for government developments. – The maximum is Five Pearls.

October 2012

32

slide-17
SLIDE 17

October 2012 17

How?

  • “An essential part of the strategy for achieving

Estidama is to fundamentally change the way we approach design, construction and real estate development”.(2.2)

  • To achieve Pearl Credit Points, under the Pearl

Rating Categories.

October 2012

33

Pearl Rating Categories(2.4)

  • Integrated Development Process
  • Natural Systems
  • Livable Buildings
  • Precious Water
  • Resourceful Energy
  • Stewarding Materials
  • Innovating Practice.

October 2012

34

slide-18
SLIDE 18

October 2012 18

Integration

  • Has

the potential to benefit from Adjudication.

  • Integrated Development Process:
  • “Encouraging cross-disciplinary teamwork to

deliver environmental and quality management throughout the life

  • f

the project”.(2.5)

October 2012

35

Innovation

  • Has the further potential to benefit from

Adjudication.

  • Innovating Practice:
  • “encouraging innovation in building design

and construction to facilitate market and industry transformation”.(2.6)

October 2012

36

slide-19
SLIDE 19

October 2012 19

Estidama

  • I propose to you; that Adjudication would be

the most effective dispute resolution procedure; for Abu Dhabi, as it:

– Integrates the team – Results in a contractually binding decision – Gives a quick solution at moderate cost.

  • Adjudication achieves Integration and would

be regarded as Innovative at present times.

October 2012

37

Implementation

  • Currently the focus of the Pearl rating system

appears to be on design and construction.

  • The benefits of adopting the most efficient

dispute resolution process are not usually considered.

  • The UPC could help to facilitate the adoption
  • f adjudication; by awarding significant credit

points for its demonstrable and beneficial use.

October 2012

38

slide-20
SLIDE 20

October 2012 20

How?

  • “An essential part of the strategy for achieving

Estidama is to …

  • fundamentally change
  • …the way we approach design, construction

and real estate development”.(2.7)

October 2012

39

Comfort Break

  • Help yourself to the refreshments.

Please wait until the end

  • f

the presentation before completing the questionnaire in your folder.

  • We will continue in 10 minutes!

October 2012

40

slide-21
SLIDE 21

October 2012 21

Dispute Resolution Survey 2012

  • Carried out between 14th June 2012 and 14th

July 2012.

  • Issued by the ICES, RICS and associated

institutions in the UAE.

  • Specific to the dispute resolution culture in

Abu Dhabi.

October 2012

41

Survey Results Generally

  • Unless stated otherwise; the results in this

presentation, are expressed in terms

  • f

percentages of the combined results of all respondents.

  • Fractions of percentages and the “It Depends”

category are not shown, for clarity. Therefore, the sum of the following percentages, does not add up to 100% .

October 2012

42

slide-22
SLIDE 22

October 2012 22

(1) Survey Results

  • 31 survey returns were made by the closing date;

comprising:

  • The detailed results can be viewed now on the

ICES UAE web site; http://www.cices.org

October 2012

43

. Clients - 21% Contractors - 31% Consultants - 48%

(2) Project Cost

  • The majority of our projects cost in excess of

US$ 100 million (AED 360 million).

October 2012

44

.

Agree 61% Disagree 6% Sometimes 13%

slide-23
SLIDE 23

October 2012 23

(3) Base Contract

  • A substantial proportion of projects use:

October 2012

45

0% 50% 100% FIDIC 4th 1987 FIDIC 1999 R&Y NEC3 Bespoke 68% 52% 3% 39% Agree Disagree Sometimes

(4) Dispute Resolution Procedures

October 2012

46

45% 3% 32% 68% 23% 29% DAB or adjudicator is appointed on an ad-hoc basis. DAB or adjudicator is appointed at commencement. Agree Disagree Sometimes

slide-24
SLIDE 24

October 2012 24

(4) Dispute Resolution Procedures cont’d

October 2012

47

74% 39% 16% 6% 39% 19% 13% 16% 48% Employer's own procedures are used. Mediation / counselling is used. An independent expert is appointed. Agree Disagree Sometim es

(5) Settlement of Disputes

October 2012

48

39% 35% 32% 29% 42% 26% 29% 23% 39% The Engineer / CA acts fairly. The Engineer / CA acts impartially. An amicable settlement is reached. Agree Disagree Sometim es

84% of Contractors disagree 64% of Contractors disagree Majority 42% of Contractors disagree

slide-25
SLIDE 25

October 2012 25

(5) Settlement of Disputes cont’d

October 2012

49

65% 0% 48% 3% 61% 26% 26% 32% 19% Disputes are usually settled before reaching arbitration. Litigation is the preferred method. Arbitration is the preferred method. Agree Disagree Sometim es

But see later statistics!

(6) Disputes Relate to:

Contract 74% Specs 68% Variations 74% EOT 97% Design 48% Const 29% 0% 20% 40% 60% 80% 100% 120%

Type of Dispute

Contract Specs Variations EOT Design Const

October 2012

50

slide-26
SLIDE 26

October 2012 26

(7) Impact of Disputes

October 2012

51

48% 32% 58% 19% 16% 13% 13% 32% 19% Increased costs more than 10%. Increased costs more than 5%. More than 3 months delay. Agree Disagree Sometim es

74% Contractors Agree 85% of Clients Agree

(8) Quicker Settlement

  • f Disputes Would

Reduce Delay 74% Reduce Cost 84% Improve Design 32% Improve Const 32% 0% 20% 40% 60% 80% 100% Agreed Impact Reduce Delay Reduce Cost Improve Design Improve Const

October 2012

52

Cognizance of previous questions and answers!

slide-27
SLIDE 27

October 2012 27

(9) Effective Methods

  • f Dispute Resolution

Arbitration 16%

Mediation 61%

Adjudication 68%

October 2012

53

Litigation 0%

(B) DISPUTES (C) COST (A) TRUST

Summing up the Statistics

In my opinion, the key statistics fall under the following heads: which I suggest are correlated with the dispute resolution procedure in the contract.

October 2012

54

slide-28
SLIDE 28

October 2012 28

Trust

  • FIDIC contract is used, without the use of the

adjudication provisions.

  • Client’s own dispute procedure is mainly used.
  • Engineer / CA; does not usually act impartially;

and sometimes acts unfairly.

  • The lack of impartiality by the dispute resolver;

leads to mistrust; a priceable Risk!

October 2012

55

Disputes

  • Disputes mainly relate to:

– Extension of time. – Interpretation of contract. – Valuation of variations. – Interpretation of drawings & specifications.

  • Which are all interrelated; resulting in risks to

time, cost and quality.

October 2012

56

slide-29
SLIDE 29

October 2012 29

Cost to the Parties

  • Projects typically cost more than U.S. $100

million.

  • With delays of

more than 3 months; due to disputes.

  • and increased costs of 5% - 10%; due to disputes.
  • That’s a Substantial Loss!

October 2012

57

Cost to the Environment

October 2012

58

One of the many costs: With an estimated annual construction expenditure for Abu Dhabi in 2011, of U.S. $100+ billion; funded substantially from oil revenue, at $80 per barrel; based on the dispute statistics, this equates to around 100+ million barrels of oil, consumed due to disputes, in just one year!

slide-30
SLIDE 30

October 2012 30

Dispute Resolution

  • Arbitration is not the preferred method.
  • A quicker settlement of disputes would reduce

delays and cost; as well as improving the quality

  • f design and construction.
  • Adjudication would be the preferred method for

settling disputes.

October 2012

59

Adjudication

  • Settles disputes impartially and quickly, which

builds trust; resulting in time and cost savings, as well as improved quality.

  • Is contractually binding, giving certainty.
  • Achieves Estidama’s tenets of Integration and

Innovation, at reduced cost; as well as being the preferable method of dispute resolution.

October 2012

60

slide-31
SLIDE 31

October 2012 31

Reflection

“We need not all agree, but if we disagree, let us not be disagreeable in

  • ur

disagreements” (Martin R. DeHaan).(6.0)

October 2012

61

Closing Thought

  • “An essential part of the strategy for

achieving Estidama is to fundamentally change …” (UPC).(2.2)

October 2012

62

slide-32
SLIDE 32

October 2012 32

Conclusion

  • Does my Hypothesis stand?
  • Based on my research and the findings of the

dispute resolution survey; I maintain my assertion that:

  • “Adjudication can significantly assist Abu

Dhabi in achieving its Estidama goals!”

October 2012

63

End of Presentation

Please return the questionnaire with your opinions; before you leave.

October 2012

64

Questions Integration Learning

slide-33
SLIDE 33

October 2012 33

Afterward

  • Your response will form part of an article on

the survey and following CPD presentation; to be published in the ICES Civil Engineering Surveyor magazine. This article will also be used as part of my dissertation for a Masters Degree in Construction Law and Arbitration.

October 2012

65

Bibliography

  • Kindly note the following that have been cited

throughout this presentation:

– (1.0) Crook JA & Betancourt JC, What is Alternative Dispute Resolution (ADR)? (CIArb, London WC1A 2LP, 2010).

  • (1.1) Ibid. @
  • p. 5; citing,

Reynolds, Michael et al. Construction Litigation Practice, (Welwyn Garden City, 2000, p.57.

  • (1.2) Ibid. @ p. 19; citing, Forgas Joseph ‘On Feeling Good

and Getting Your Way: Mood Effects on Negotiator Cognition and Bargaining Strategies’, (1998) 74 Journal of Personality and Social Psychology, p. 565.

  • (1.3) Ibid. @ p. 15; citing, Menkel-Meadow, Carrie, ‘Lawyer

Negotiations: Theories and Realities-What we Learn from Mediation’, (1993) 56 Modern Law Review, p. 372.

October 2012

66

slide-34
SLIDE 34

October 2012 34

Bibliography cont’d

– (1.0) Crook JA & Betancourt JC, What is Alternative Dispute Resolution (ADR)? ; cont’d

  • (1.4) Ibid. @ p. 5; citing, Levine, David, ‘Early Neutral

Evaluation: A Follow-Up Report’, (1986) 70 Judicature,

  • p. 237.
  • (1.5) Ibid. @ p. 9; citing, Jones, Doug, ‘Expert

Determination in Commercial Contracts’ in Cato, Mark, The Expert in Litigation and Arbitration (London, 1999),

  • p. 789.
  • (1.6) Ibid. @ p. 9; citing, Wright, Ian, et al. ‘Alternative

Dispute Resolution’ in Ramsey, Vivian et al., Construction Law Handbook (London, 2009), p. 905.

October 2012

67

Bibliography cont’d

– (2.0) Abu Dhabi Urban Planning Council (UPC), The Pearl Rating System for Estidama, Version 1.0 (UPC, Emirate of Abu Dhabi, April 2010).

  • (2.1) Ibid. @ p. 14.
  • (2.2) Ibid. (emphasis added).
  • (2.3) Ibid.
  • (2.4) Ibid. @ p. 1.
  • (2.5) Ibid.
  • (2.6) Ibid.
  • (2.7) Ibid. @ p. 14. (emphasis added).
  • (2.8) Ibid.

October 2012

68

slide-35
SLIDE 35

October 2012 35

Bibliography cont’d

– (3.0) Abu Dhabi Commercial Conciliation and Arbitration Center (ADCCAC), Procedural Regulations 2005. – (4.0) Gaitskell R QC, Trends – dispute resolution in the credit crunch (Construction Law International Journal, Vol. 6, issue 3, October 2011) @ p. 6-12.

October 2012

69

Bibliography cont’d

– (5.0) Giblin L, The Art of Dealing With People (Embassy Books, Mumbai 400 023, 2001); at p. 48. – (6.0) Taddeo D, Notable Quotables “3,000 Quotations from A to Z” (Creation House Press, Florida 32746); at p. 39.

October 2012

70

slide-36
SLIDE 36

October 2012 36

Disclaimer

This survey and/or presentation material may not be used for any commercial purposes whatsoever. The

  • pinions

expressed in this survey and/or presentation, do not necessarily reflect the views of the Chartered Institution

  • f

Civil Engineering Surveyors (ICES), its Council of Management or

  • ther committees or members, or those involved in

conducting the survey. No material may be reproduced in whole or in part without the written permission of the ICES. END.

October 2012

71